PJSC Stroytransgaz has completed the construction of bridge crossing in the Volokolamsky District one month ahead of the schedule. The works began in June and were finished on the 18th of August. The bridge with a total length of almost 60 meters is located at the 17th km of Lotoshino-Suvorovo-Klin motor road and crosses the Lama River in Yaropolets settlement.

In accordance with the contract, the bridge pylons have been repaired, the bank slopes have been reinforced, the modern waterproofing system has been installed, the asphalt concrete cover has been replaced, and the road surface marking has been restored. Guardrails and handrails allowing for high security levels have been also installed.

The bridge traffic has been completely suspended during the repairs. Specific bypass routes have been developed.

It if the firs bridge crossing constructed by STG PJSC at the request of Mosavtodor State-Financed Organisation as a part of the project on the overhaul of the Moscow Region bridge-type objects.

In accordance with the contract, PJSC Stroytransgaz will repair one of the flyovers at the 35th km of Kashirskoe highway, one pontoon bridge across the Moskva River near Cherkizovo settlement and 8 bridge crossings in various districts of the Moscow region.