Photo Report of the Nizhny Novgorod Stadium Construction

Photo Report of the Nizhny Novgorod Stadium Construction

See the photo report of the Nizhny Novgorod Stadium construction in January 2017

Installation of the roof frame is in progress at the Nizhny Novgorod Stadium. At the moment the builders have finished assembling the metal work over the stands, and proceed with installation of the frame above the lobby zone. The total weight of the roof (without regard to the covering) will exceed 10,000 tons; as of today over 7,700 tons of the metal work have been installed.

At the same time the builders continue to install utility systems both inside the stadium building and outside its perimeter. Walls and partitions are being set up in all sectors. The specialists have commenced assembly of the lifting equipment in sector A.

Over 1300 workers are involved in the stadium construction.