Kazakhstan, Kazakhstan
Mineral Resources and Energy Sector Infrastructure Council of Kyzylorda
2004-2005 гг.
300 km
In 2004, STG entered into the contract for implementation of gasification project in Kyzylorda. Mineral Resources and Energy Sector Infrastructure Council of Kyzylorda was the customer for the project for transferring of housing sector in Kyzylorda to associated petroleum gas.
Under the contract, STG as a general contractor developed the required documentation, completed the design and construction of decentralized heating systems, constructed high and low pressure polyethylene gas pipelines of over 300 km and twenty gas distribution stations, supplied the contracted equipment.
STG also designed and integrated the advanced metering system, performed testing, pre-commissioning, commissioning and training of the operating personnel.
This project became the first one in the history of Kazakhstan to provide associated gas to residential area.
The project was completed in 2005.